Up to 600,000 NVIDIA GPUs over three years (KSA and US); xAI 500MW+ flagship; AWS "AI Zone" up to 150,000 GPUs.

Not yet
Claim made
Who
HUMAIN / NVIDIA / xAI / AWS
Target date
~Nov 2028
Status checked
24 October 2026

Source

Evidence to date

19–20 Nov 2025: US authorised HUMAIN to buy the equivalent of up to 35,000 GB300 chips (The National, 20 Nov 2025 Page read: Source page fetched and read directly). 22 Oct 2026: HUMAIN expanded its NVIDIA deal with an 84MW plan (about 27,000 GPUs): 14MW (about 6,000 Blackwell GPUs) deploying from Q4 2026, then 70MW of Vera Rubin systems from mid-2027 (The National, 22 Oct 2026 Page read: Source page fetched and read directly). No published delivery figures against the 600,000-GPU total, and no commissioning of the xAI site or the AWS "AI Zone", found in checks on 24 Oct 2026.

Next indicator

Delivery and commissioning announcements