Campus work "on track" despite redesign.

Claim made
Who
G42 (via Reuters/CNBC)
Target date
None stated
Status checked
28 September 2026

Source

CNBC [F]

Evidence to date

Milestones exist only for the first phase: about 300MW operational in the UAE, about 370MW under construction (Khaleej Times, 13 Aug 2026). No published plan for the redesigned 5GW network. Classified conservatively.

Next indicator

Official redesign plan; phase timelines