Tracker

Tracker ID CR-C02

First 200MW phase "in place and ready at some point in the third quarter" of 2026.

Not yetCompany-reported
Claim made
Who
Khaldoon Al Mubarak (Mubadala)
Target date
30 Sep 2026
Status checked
24 October 2026

Source

Evidence to date

The 30 Sep 2026 target date passed with no in-service announcement. 4 Sep 2026: the builder, Khazna, said it expects to deliver the first 200MW in the fourth quarter of 2026 (Bloomberg via The Nightly, 4 Sep 2026 Page read: Source page fetched and read directly). No in-service announcement found in primary or Gulf sources as of 24 Oct 2026. The 30-day grace period ends on 30 Oct 2026.

Next indicator

Status decision on 30 Oct 2026; the Q4 2026 target is tracked under CR-C01

Where this claim appears